Bayshore Safety & Industrial Supplies Guide
Extension cord gauge and length by amperage, and what OSHA requires on a jobsite cord? Reading the cord jacket (12/3 SJTW), the NEC ampacity table, voltage drop over 50 and 100 feet, why a 16 gauge cord starves a saw, hard vs junior hard service, the no-splice and no-doorway rules, GFCI protection, and inspecting the plug, jacket and ground pin
An extension cord is read off its jacket: 12/3 SJTW means 12 AWG conductors, three of them (hot, neutral, ground), in a junior hard service (SJ) thermoplastic (T) weather-resistant (W) jacket. The gauge sets how much current the cord can carry and how much voltage it loses over its length. NEC Table 400.5(A)(1) gives the ampacity for flexible cord with three current-carrying conductors: 18 AWG 7 amps, 16 AWG 10, 14 AWG 15, 12 AWG 20, 10 AWG 25 (the two-conductor column is higher; the cord maker prints the rating on the tag). Length then takes voltage: the makers’ charts, built on the NEC’s 3 percent recommended drop, put a 15 amp tool on 14 AWG to 50 feet and 12 AWG to 100 feet, a 20 amp tool on 12 AWG to 50 feet and 10 AWG to 100, and keep 16 AWG for lights and loads under 10 amps and short runs; a tool on a cord too light for it runs hot, loses torque and burns its motor. OSHA’s construction rules: 1926.405(a)(2)(ii)(J) requires extension cords used with portable tools to be three-wire and designed for hard or extra-hard usage (types S, ST, SO, STO, SJ, SJO, SJT, SJTO and their W-marked outdoor versions; household lamp cord is not allowed); 1926.405(a)(2)(ii)(I) requires cords protected from damage and not run through doorways and pinch points unless protected; 1926.405(g)(2)(iii) allows no splices or taps except a repair on a 12 AWG or larger cord that restores the original insulation; 1926.404(b)(1) requires GFCI protection or an assured equipment grounding conductor program for every cord set on a site; and 1926.416(e) and 1910.334(a) require cords inspected before use and removed when the jacket is cut, the plug is damaged or the ground pin is missing. The band lists the cords, GFCI cords and adapters, plugs and cord reels we stock by gauge and length.
Why the tool is slow at the end of the cord. Every foot of copper has resistance; a 100 foot 16 gauge cord feeding a 15 amp saw drops the voltage at the saw by more than 10 percent, so the motor draws more current to do the same work, heats, and dies young. The gauge is chosen for the amps and the length together, and the OSHA rules add the jacket type, the ground, the GFCI and the inspection. The cards go through the jacket code, the ampacity table, length, the rules, and inspection.
Extension cords, question by question
Ampacities are NEC Table 400.5(A)(1); length guidance is the makers’ charts; the rules are 1926.405, 1926.404 and 1926.416.
In plain words
- 12/3 SJTW: 12 gauge, three wires, junior hard service, thermoplastic, outdoor.
- Ampacity: 16 gauge 10 to 13 amps, 14 gauge 15, 12 gauge 20, 10 gauge 25.
- Length: 15 amps on 14 gauge to 50 feet and 12 gauge to 100; 20 amps on 12 to 50 and 10 to 100.
- Jobsite cords: three-wire, S or SJ type, W outdoors; no splices under 12 gauge; not through doors or holes unprotected.
- GFCI or an assured grounding program on every cord set (1926.404(b)(1)).
- Inspect every shift: ground pin, plug, jacket; damaged cords out.
Questions people ask
What gauge extension cord for a 15 amp tool?
The makers’ charts list 14 AWG to 50 feet and 12 AWG to 100 feet; 16 AWG is for loads under 10 amps and short runs.
What does 12/3 mean on an extension cord?
12 AWG conductors, three of them: hot, neutral and ground.
Can you splice an extension cord?
Only a hard service cord 12 AWG or larger, with a repair that restores the original insulation and jacket (1926.405(g)(2)(iii)); otherwise no splices or taps.
Does OSHA require GFCI on extension cords?
On construction sites, every 120 volt 15 and 20 amp receptacle not part of permanent wiring, including cord ends, has GFCI protection or is in an assured equipment grounding program (1926.404(b)(1)).
Can a cord run through a doorway?
Only if protected from damage at the pinch point (1926.405(a)(2)(ii)(I)); never through holes in walls, floors or ceilings.
Is a cord with a broken ground pin OK to use?
No; it is a defect under 1926.416(e) and 1910.334(a) and the cord is removed until the plug is replaced.
Related guides
GFCI and assured equipment grounding on construction sitesThe 1926.404(b)(1) program in detailFlashlight ratings, lumens, runtime and intrinsically safeLighting the workWelding cable size and connectorsThe welding-side cable rulesWhat PPE should an electrician wear?Working on energized equipmentOSHA hand and power tool rules1926.302(a) electric toolsCable ties: tensile strength and UV ratingSecuring cords and cableThe ratings, test results and standards shown here are the manufacturers' published values, reproduced as published. Nothing on this page is a recommendation by Bayshore Safety that any product is suitable for a particular task, hazard or workplace. Selecting safety products and protective equipment is the responsibility of the end user and the employer, based on their own hazard assessment and the regulations that apply to their work. Confirm every value on the manufacturer's own documentation before use.